The following is a summary of the work completed in the Center Business District last week and the work P. Gioioso & Sons, Inc.  has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Construction Updates and Schedule:

Work completed this week through December 4:

• Removed all temporary water bypass piping and hosing, and continue site clean-up on Cottage Park Rd., between Somerset Ave. and Pleasant St.; and on Somerset Ave., between Cottage Park Rd. and Pleasant St.

• Completed installation of sewer service connections to new sewer main for properties on Adams St., between Woodside Ave. and Bartlett Rd.; and on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continued installation of sewer service connections to new sewer main for properties and businesses on Bartlett Rd., between French Sq. and Adams St.; and on Somerset Ave., between Cottage Park Rd. and Pleasant St.

• Completed paving of various roadway and sidewalk areas on Pauline St., Hagman Rd., and Woodside Ave.

• Installed new hydrant on Woodside Ave., at Pleasant St.

• Continued construction of the new storm drain in the following locations:

• Woodside Ave., between French Sq. and Pleasant St.

• Pleasant St., at Woodside Ave.

• Somerset Ave., between Woodside Ave. and Cottage Park Rd.

• Adams St., between Bartlett Rd. and Williams St.

Two-Week Anticipated Schedule:

1. December 7 to December 11, 2020

Continue installation of sewer service connections to new sewer main for properties and businesses on Bartlett Rd., at French Sq., and on Somerset Ave., between Cottage Park Rd. and Pleasant St.

Continue construction of the new storm drain in the following locations:

 i. Woodside Ave., at French Sq.

ii. Somerset Ave., between Woodside Ave. and Cottage Park Rd.

iii. Bartlett Rd., between French Sq. and Adams St.

Continue site-clean up within Project limits and all staging/stockpile areas.

2. December 14 to December 15, 2020

Continue site-clean up within Project limits and all staging/stockpile areas. 

*All construction activities are scheduled to conclude for Winter Moratorium at end of workday on Tuesday, December 15.

Transcript Staff

Recent Posts

St. John’s Episcopal Church Spring Craft Fair

Luca DePhamphillis, 7, with his nina, Pam Evans, hooking a Charmander Pokémon necklace around her…

5 days ago

Lieutenant Lessard Remembered for His Caring and Department Initiatives

Retired Winthrop Police Lt. David Lessard, 69 died last Friday after a long battle with…

5 days ago

Marino Looks to Possible Debt Exclusion for School Budget Needs

By Adam Swift The town is looking toward a possible debt exclusion vote in the…

5 days ago

Town Manager Presents Capital Plan at Spring Forum

By Adam Swift As part of the Annual Spring Forum on Tuesday night, Town Manager…

5 days ago

News Brief

Winthrop Police Department Awarded Car Seat Distribution Grant  Police Chief John Goodwin is pleased to…

5 days ago

State and City Officials Meet With La Colaborativa on Shelter Operation Plans in Chelsea

By Adam Swift State and Chelsea officials, along with local nonprofit La Colaborativa, have spent…

5 days ago