Construction Update: Upcoming Schedule of Work in the Center Business District

Special to the Transcript

The following is a summary of the work completed in the Center Business District Project  and the work P. Gioioso & Sons, Inc.  has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Work completed:

• Completed construction of the new water main on Somerset Ave., between Cottage Park Rd. and Pleasant St.

• Continued installation of sewer service connections to new sewer main for residences/businesses on Woodside Ave., between Hagman Rd. and Pleasant St.

• Began installation of water service connections to new water main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Began installation of sewer service connections to new sewer main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continued construction of the new storm drain on Woodside Ave., between Somerset Ave. and Hagman Rd. Installed new drain manholes and drain pipe.

• Installed temporary trench pavement for trenches excavated on Somerset Ave., Cottage Park Rd., and Woodside Ave.

Anticipated Schedule (Nov. 9-20):

1. November 9 to November 13, 2020

• Work will be performed on Veterans Day (November 11, 2020).

• Normal Working Hours (7 AM – 3:30 PM):

• Continue installation of water service connections to new water main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continue installation of sewer service connections to new sewer main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Begin construction of the new storm drain on Woodside Ave., between Hagman Rd. and Pleasant St. Install new drain manholes and drain pipe.

• Night Work (Monday – Thursday, 8 p.m. – 6 a.m.)

• Continue construction of the new storm drain on Woodside Ave. at French Sq. Install new catch basins and drain pipe.

• Continue construction of the new water main on Woodside Ave. at French Sq.

• Continue installation of sewer service connections to the new sewer main on Woodside Ave. at French Sq.

2. November16 to November 20

• Night work is anticipated to end on November 13.

• Continue installation of water service connections to new water main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continue installation of sewer service connections to new sewer main for residences on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continue construction of the new storm drain on Woodside Ave., between Hagman Rd. and Pleasant St. Install new drain manholes and drain pipe.

• Continue construction of the new storm drain on Somerset Ave., between Woodside Ave. and Pleasant St. Install new drain manholes, catch basins, and drain pipe.

Notices:

1. Night Work: construction of storm drain, water main, and water and sewer services on Woodside Ave. at French Square will be performed from 8 p.m. and 6 a.m., Monday night through Thursday night. No construction is planned for Friday night, Saturday night, or Sunday night. When night work begins, construction activities will occur during normal work hours (7 AM to 3:30 PM) as well as night hours (8 p.m. to 6 a.m.). Night work is scheduled to be completed by 6 a.m. Friday, November 13. Temporary parking restrictions will be required for portions of the parking lot in French Square during night-hours; notices will be posted in these locations with restricted hours/dates.

Residents and businesses with temporary water service connections (blue hoses) are requested not to move these hoses or shut off the outside faucet the hoses are connected to.  The hoses provide your property with water service during construction. If the outside faucet is closed, it will interrupt your water service.  If the hose is moved it can create a trip hazard where the temporary water service crosses the sidewalk.  Please do not move these hoses to perform yard work. If you have landscaping services at your property, please inform your landscaper not to move these hoses or shut off the outside faucet.  Running over these hoses with a lawn mower cut the hoses and interrupt water service until the hose can be replaced.  If you see a trip hazard, please contact Frank Fruci (P. Gioioso & Sons, Inc.) at (617) 592-3784 immediately to report the hazard.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.