The following is a summary of the work completed this week and the work P. Gioioso & Sons, Inc. (contractor) has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.
Construction Updates and Schedule:
Work completed this week (9/14/20 to 9/18/20):
• Completed construction of the new water main on Adams St., between Bartlett Rd. and Woodside Ave.
• Began construction of the new sewer main on Somerset Ave., between Cottage Park Rd. and Pleasant St.
• Continued construction of the new storm drain on Hagman Rd., between Pauline St. and French Square. Installed new drain manholes, catch basins, and drain pipe.
• Began installation of permanent water service connections to new water main for residences/businesses on Somerset Ave., between Woodside Ave. and Cottage Park Rd.
• Installed temporary trench pavement for trenches excavated on Adams St., Somerset Ave. and Hagman Rd.
Two-week
Anticipated Schedule through 10/2/20
1. September 21 to September 25, 2020
• Continue construction of the new sewer main on Somerset Ave., between Cottage Park Rd. and Pleasant St.
• Continue construction of the new storm drain on Hagman Rd., between Pauline St. and French Square. Install new catch basins and laterals.
• Begin construction of the new storm drain on Woodside Ave., between Pauline St. and Somerset Ave. Install new drain manholes, catch basins and drain pipe.
• Continue installation of permanent water service connections to new water main for residences/businesses on Somerset Ave., between Woodside Ave. and Cottage Park Rd.
• Continue installation of permanent sewer service connections to new sewer main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; and on Adams St., between Woodside Ave. and Williams St.
• Install temporary trench pavement for trenches excavated on Somerset Ave., Hagman Rd., Woodside Ave., Bartlett Rd. and Adams St.
2. September 28 to October 2, 2020
• Continue construction of the new sewer main on Somerset Ave., between Cottage Park Rd. and Pleasant St.
• Continue construction of the new storm drain on Woodside Ave., between Pauline St. and Somerset Ave. Install new drain manholes, catch basins and drain pipe.
• Continue installation of permanent sewer service connections to new sewer main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; and on Adams St., between Woodside Ave. and Williams St.
• Begin installation of permanent water service connections to new water main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; on Adams St., between Woodside Ave. and Williams St.; and on Williams St., between Adams St. and Pleasant St.
• Install temporary trench pavement for trenches excavated on Somerset Ave., Woodside Ave., Bartlett Rd., Adams St. and Williams St.
NOTICES:
1. Night Work: Night work to construct storm drain, water main and water and sewer services in Woodside Ave. at French Square is schedule to begin in October. The tentative start date for this work is Monday night, October 5, 2020. Work hours during night work will be 8 PM to 6 AM, Monday through Thursday. The work is anticipated to take approximately 3-weeks to construct. When night work begins, construction activities will occur during normal work hours (7 AM to 3:30 PM) as well as night hours (8 PM to 6 AM).
2. Hagman Rd. and Citizens Bank Drive Thru: Hagman Road will be closed to vehicle traffic during work hours at French Sq. Citizens Bank Drive Thru window can be accessed from Putnam Street during this time. Police Details and detour signs will be in place.
Residents and businesses with temporary water service connections (blue hoses) are requested not to move these hoses or shut off the outside faucet the hoses are connected to. The hoses provide your property with water service during construction. If the outside faucet is closed, it will interrupt your water service. If the hose is moved it can create a trip hazard where the temporary water service crosses the sidewalk. Please do not move these hoses to perform yard work. If you have landscaping services at your property, please inform your landscaper not to move these hoses or shut off the outside faucet. Running over these hoses with a lawn mower cut the hoses and interrupt water service until the hose can be replaced. If you see a trip hazard, please contact Frank Fruci (P. Gioioso & Sons, Inc.) at (617) 592-3784 immediately to report the hazard. Occasionally, residents and businesses may experience discolored tap water because of construction activities. Construction may disrupt sediment in water pipes and cause it to become suspended in the water. Discolored water is not a health threat and is the result of low levels of naturally occurring iron in water. If you are experiencing water discoloration, flush your water from a faucet that does not have a screen (like the bathtub or outside spigot) until you get clear water. If your water is still discolored after several minutes of flushing, you may need to wait a few hours for the sediment to settle and the water in the main to clear. Additionally, residents and businesses may also experience warm tap water due to the sun heating the temporary water mains. Similarly, please flush your water for several minutes until it has cooled.