Categories: News

Construction Update: Center Business District Project updates

Special to the Transcript

The following is a summary of the work completed this week and the work P. Gioioso & Sons, Inc. (contractor) has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Reclaiming of road surface
on Bartlett Road, between
French Square and Pleasant Street.

Two-Week Anticipated

Schedule through 7/30/21

1. July 19 to July 30, 2021:

a.      Scheduled Work:

   i.    Begin installation of electric conduit on Woodside Avenue, between Pauline Street and French Square.

   ii.   Begin resetting existing granite curb and installing new concrete sidewalks on Somerset Avenue.

b.      Traffic Management (M-F, 7 AM to 4 PM):

   i.    The CBD can be accessed from Cottage Park Road, Woodside Avenue (from Pleasant Street), and Jefferson Street during construction hours (7 AM to 4 PM). Hagman Road, Jefferson Street, and Bartlett Road will be open during construction hours (7 AM to 4 PM) to exit the CBD. 

   ii.   Woodside Avenue will be closed at Pauline Street. Access will be permitted to local residents and businesses.

   iii.  Somerset Avenue will be closed at Pleasant Street.

2.  July 26 to July 30

a.      Scheduled Work:

   i.    Continue installation of electric conduit on Woodside Avenue, between Pauline Street and French Square.

   ii.   Begin installation of electrical conduit on Pauline Street and Hagman Road.

   iii.  Continue resetting granite curb and installing new concrete sidewalk on Somerset Avenue.

b.    Traffic Management (M-F, 7 AM to 4 PM ):

   i.    The CBD can be accessed from Cottage Park Road, Woodside Avenue (from Pleasant Street), and Jefferson Street during construction hours (7 AM to 4 PM). Hagman Road, Jefferson Street, and Bartlett Road will be open during construction hours (7 AM to 4 PM) to exit the CBD. 

   ii.   Woodside Avenue will be closed at Pauline Street. Access will be permitted to local residents and businesses.

   iii.     Somerset Avenue will be closed at Pleasant Street.

Transcript Staff

Recent Posts

St. John’s Episcopal Church Spring Craft Fair

Luca DePhamphillis, 7, with his nina, Pam Evans, hooking a Charmander Pokémon necklace around her…

5 days ago

Lieutenant Lessard Remembered for His Caring and Department Initiatives

Retired Winthrop Police Lt. David Lessard, 69 died last Friday after a long battle with…

5 days ago

Marino Looks to Possible Debt Exclusion for School Budget Needs

By Adam Swift The town is looking toward a possible debt exclusion vote in the…

5 days ago

Town Manager Presents Capital Plan at Spring Forum

By Adam Swift As part of the Annual Spring Forum on Tuesday night, Town Manager…

5 days ago

News Brief

Winthrop Police Department Awarded Car Seat Distribution Grant  Police Chief John Goodwin is pleased to…

5 days ago

State and City Officials Meet With La Colaborativa on Shelter Operation Plans in Chelsea

By Adam Swift State and Chelsea officials, along with local nonprofit La Colaborativa, have spent…

5 days ago