Construction Update: What’s Going on in the Center Business District

The following is a summary of the work completed this week and the work P. Gioioso & Sons, Inc. (contractor) has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Construction Updates and Schedule:

Work completed this week (5/3/21 to 5/7/21):

• Construction of storm drain improvements on Somerset Avenue, between Cottage Park Road and Pleasant Street.

Two-Week Anticipated Schedule

(5/10/21 to 5/21/21)

May 10 to May 14, 2021:

Scheduled Work:

• Construction of storm drain improvements on Somerset Avenue between Cottage Park Road and Pleasant Street.

Traffic Management (M-F 5/10 to 5/14; 7 AM to 4 PM):

• The CBD can be accessed from Cottage Park Road, Woodside Avenue, and Jefferson Street during construction hours (7 AM to 4 PM). Hagman Road and Bartlett Road will be open during construction hours (7 AM to 4 PM) to exit the CBD.

• Somerset Avenue will be closed at Pleasant Street. Access will be permitted to local residents and businesses.

May 17 to May 21, 2021

Scheduled Work:

• Construction of storm drain improvements on Somerset Avenue, between Cottage Park Road and Pleasant Street.

• Construction of storm drain improvements on Cottage Park Road, at the intersection of Somerset Avenue, and on Cottage Park Road between Somerset Avenue and Pleasant Street.

Traffic Management (Somerset Avenue work; 7 AM to 4 PM):

The CBD can be accessed from Woodside Avenue, Jefferson Street and Cottage Park Road during construction hours (7 AM to 4 PM). Hagman Road and Bartlett Road will be open during construction hours (7 AM to 4 PM) to exit the CBD.

Somerset Avenue will be closed at Pleasant Street. Access will be permitted to local residents and businesses.

Traffic Management (Cottage Park Road work; 7 AM to 4 PM):

The CBD can be accessed from Woodside Avenue and Jefferson Street during construction hours (7 AM to 4 PM). Hagman Road and Bartlett Road will be open during construction hours (7 AM to 4 PM) to exit the CBD.

Somerset Avenue and Cottage Park Road will be closed at Pleasant Street. Access will be permitted to local residents and businesses.

Transcript Staff

Recent Posts

Special Delivery: Vikings defeat Essex Tech, 28-18, in season opener

There were several memorable football plays Friday night in the village of Hathorne in the…

2 days ago

Winthrop Town Council considers new tree plan

Winthrop officials are considering a plan that would help provide more trees tied to new…

2 days ago

Town Council votes to no longer set taxi fares

The Winthrop Town Council is officially out of the taxi fare rate setting business. Last…

2 days ago

Winthrop officials discuss WCAT close captioning

The town is looking at the possibility of providing close captioning for WCAT municipal meeting…

2 days ago

Drought conditions improve across Massachusetts

Energy and Environmental Affairs (EEA) Secretary Rebecca Tepper declared the Central Region has returned to…

2 days ago

Aquarium offering discounts for homeschooling families

The New England Aquarium is offering discounted admission this fall for homeschooling families to experience…

2 days ago