Center Business District Construction Look-Ahead

Special to the Transcript

Construction of the Center Business District Infrastructure Improvements project has resumed on March 22. The following is a summary of the work P. Gioioso & Sons, Inc. (contractor) has scheduled for the next two weeks. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Two-Week Anticipated Schedule:

Through March 26, 2021

• Construction of sewer improvements at the intersection of Putnam Street and Jefferson Street.

• Construction of storm drain improvements between French Square and Putnam Street.

• Traffic Management:

      i.      The CBD can be accessed from Woodside Avenue and Somerset Avenue during construction hours (7 AM to 4 PM).

     ii.      Putnam Street will be closed to through traffic. Access will be permitted to local residents and businesses between Buchanan Street and Jefferson Street.

    iii.      Jefferson Street will be closed at Fremont Street.

    iv.      Putnam Street will be closed at the Citizens Bank.  Access to Michael’s Mall and Citizens Bank will remain open. Access to businesses will be maintained.

    v.      Jefferson Street will be closed at French Square. Access to businesses will be maintained.

March 29 to April 2

• Construction of storm drain improvements on Jefferson Street between French Square and Putnam Street and in the intersection of Putnam Street and Jefferson Street. 

• Traffic Management:

    i.      The CBD can be accessed from Woodside Avenue and Somerset Avenue during construction hours (7 AM to 4 PM).

   ii.      Putnam Street will be closed to through traffic. Access will be permitted to local residents and businesses between Buchanan Street and Jefferson Street.

   iii.      Jefferson Street will be closed at Fremont Street.

   iv.      Putnam Street will be closed at the Citizens Bank.  Access to Michael’s Mall and Citizens Bank will remain open. Access to businesses will be maintained.

   v.      Jefferson Street will be closed at French Square. Access to businesses will be maintained.

Transcript Staff

Recent Posts

Annual Chamber of Commerce Community Awards

Supt. of Schools Lisa Howard joins Winthrop Middle School teachers in congratulating Frank Alexander Brown,…

6 days ago

Special Town Council Meeting Called for 3A Vote

By Adam Swift The town council met for a brief special meeting on Wednesday, April…

6 days ago

Town Manager Tracks Grant Losses

By Adam Swift At the request of the town council, Town Manager Tony Marino has…

6 days ago

News Brief

Precinct 2 Town Hall Set for April 22 Precinct 2 Town Councilor Kim Dimes will…

6 days ago

School Committee Presents Final Settlement Proposal; Calls for Membership Consideration

Special to the Transcript The Winthrop School Committee has presented the Winthrop Teachers Association (WTA)…

6 days ago

Rules Disagreement Draws Out End of Council Meeting

By Adam Swift The town council held a regular meeting on Tuesday, April 7. And…

6 days ago