Upcoming Schedule of Work in the Center Business District

The following is a summary of the work completed last week and the work P. Gioioso & Sons, Inc. (contractor) has scheduled for the next two weeks for the Center Business District. Please note, the anticipated schedule may vary due to unforeseen site conditions, weather conditions, or other factors out of the contractor’s control.

Work completed through October 9:

Began construction of the new sewer main on Cottage Park Rd., between Somerset Ave. and Pleasant St.

Continued construction of the new storm drain on Woodside Ave., between Pauline St. and Somerset Ave. Installed new drain manholes, catch basins and drain pipe.

Continued installation of water service connections to new water main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; and on Adams St., between Woodside Ave. and Bartlett Rd.

Installed temporary trench pavement for trenches excavated on Cottage Park Rd., Woodside Ave., Bartlett Rd., and Adams St.

Anticipated Schedule through 10/23/20:

1. October 13 to

 October 16, 2020

• No construction will occur on Monday, October 12th, in observation of the Columbus Day holiday.

• Continue construction of the new sewer main on Cottage Park Rd., between Somerset Ave. and Pleasant St.

• Continue construction of the new storm drain on Woodside Ave., between Pauline St. and Somerset Ave. Install new catch basins and drain pipe.

• Begin installation of sewer service connections to new sewer main for residences/businesses on Woodside Ave., between Hagman Rd. and Pleasant St.

• Continue installation of sewer service connections to new sewer main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; and on Adams St., between Woodside Ave. and Bartlett Rd.

• Continue installation of water service connections to new water main for residences on Adams St., between Woodside Ave. and Bartlett Rd. Remove temporary water bypass piping on Bartlett Rd., Adams St., and Williams St.

• Install temporary trench pavement for trenches excavated on Cottage Park Rd., Woodside Ave., Bartlett Rd., and Adams St.

2. October 19 to

October 23, 2020

• Begin construction of the new water main on Cottage Park Rd., between Somerset Ave. and Pleasant St. This work will be completed during normal working hours (7 AM – 3:30 PM).

• Continue installation of sewer service connections to new sewer main for residences/businesses on Bartlett Rd., between French Square and Pleasant St.; and on Adams St., between Woodside Ave. and Bartlett Rd. This work will be completed during normal working hours (7 AM – 3:30 PM).

• Begin construction of the new storm drain on Woodside Ave., between Somerset Ave. and Hagman Rd.; and in temporary parking lot in French Square. Install new drain manholes and drain pipe. This work will be completed during night working hours (Monday – Thursday, 8 PM – 6 AM). See notice below regarding night work.

• Install temporary trench pavement for trenches excavated on Cottage Park Rd., Bartlett Rd., Adams St., Woodside Ave., and French Square parking lot.

Notices:                  

1. Night Work: Beginning Monday, October 19th, construction of storm drain, water main, and water and sewer services on Woodside Ave. at French Square will be performed from 8 PM and 6 AM, Monday night through Thursday night. No construction is planned for Friday night, Saturday night, or Sunday night. When night work begins, construction activities will occur during normal work hours (7 AM to 3:30 PM) as well as night hours (8 PM to 6 AM). Night work is scheduled to be completed by 6 AM Friday, November 6th. Temporary parking restrictions will be required for portions of the parking lot in French Square during night-hours; notices will be posted in these locations with restricted hours/dates.

Residents and businesses with temporary water service connections (blue hoses) are requested not to move these hoses or shut off the outside faucet the hoses are connected to.  The hoses provide your property with water service during construction. If the outside faucet is closed, it will interrupt your water service.  If the hose is moved it can create a trip hazard where the temporary water service crosses the sidewalk.  Please do not move these hoses to perform yard work. If you have landscaping services at your property, please inform your landscaper not to move these hoses or shut off the outside faucet.  Running over these hoses with a lawn mower cut the hoses and interrupt water service until the hose can be replaced.  If you see a trip hazard, please contact Frank Fruci (P. Gioioso & Sons, Inc.) at (617) 592-3784 immediately to report the hazard.

Occasionally, residents and businesses may experience discolored tap water because of construction activities. Construction may disrupt sediment in water pipes and cause it to become suspended in the water.  Discolored water is not a health threat and is the result of low levels of naturally occurring iron in water. If you are experiencing water discoloration, flush your water from a faucet that does not have a screen (like the bathtub or outside spigot) until you get clear water.  If your water is still discolored after several minutes of flushing, you may need to wait a few hours for the sediment to settle and the water in the main to clear. Additionally, residents and businesses may also experience warm tap water due to the sun heating the temporary water mains. Similarly, please flush your water for several minutes until it has cooled.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.